Hydropower projects in Arunachal Pradesh require multi-level approvals and are monitored through several specialized committees ensuring environmental, social, and technical compliance.
Clearance Framework
Multi-Level Approvals
Projects progress through sequential clearances:
- Environmental Clearance (Ministry of Environment, Forest and Climate Change)
- Forest Clearance (Forest Department, Government of India)
- Wildlife Clearance (Ministry of Environment, Forest and Climate Change)
- LADF Approval (State Level Monitoring Committee)
- Operational Clearance (Ministry of Power)
Oversight Committees
Concession Committee
Function: Grant hydropower concessions through transparent bidding
Composition:
- Chief Secretary (Chair)
- Secretary, Water Resources
- Secretary, Forest
- DHPD Commissioner
- Government Representatives
- Technical Experts
Responsibilities:
- Project bidding management
- Developer evaluation
- Concession agreement finalization
- Performance conditions setting
- Dispute resolution
Authority: Final decision on concession award
Download Concession Committee Order (PDF)
State Level Monitoring Committee (SLMC)
Function: Project-specific environmental and social compliance monitoring
Composition:
- District Collector (Chair)
- DHPD representative
- Forest Department representative
- Environment Department representative
- Project developer
- NGO representative
- Community representatives
Responsibilities:
- Environmental compliance verification
- Social safeguard implementation monitoring
- LADF management oversight
- Grievance redressal
- Compliance reporting
- Site inspections and verification
Frequency: Quarterly meetings, monthly site inspections
Jurisdiction: Project-specific from concession to operation
Download SLMC Guidelines (PDF)
State Technical and Empowered Committee (STEC)
Function: Technical review and clearance recommendations
Established: Committee Order 2021
Composition:
- Chief Secretary / Secretary (Chair)
- DHPD Commissioner
- Chief Engineers
- Environmental experts
- Social experts
- Technical consultants
Responsibilities:
- Technical design review
- Environmental assessment evaluation
- Social impact assessment
- Clearance recommendation
- Exception/exemption consideration
- Technical dispute resolution
Authority: Makes technical recommendations to approving ministry
Download STEC Committee Order 2021 (PDF)
Standing Committee for 13 Projects
Function: Coordinate and monitor specific project cluster (13 strategic projects)
Composition:
- DHPD Commissioner (Chair)
- Project-specific Chief Engineers
- Developer representatives
- Technical consultants
- Government liaison officers
Responsibilities:
- Project-cluster coordination
- Schedule management
- Infrastructure integration
- Benefit sharing
- Cross-project issues resolution
- Cumulative impact management
Scope: 13 major hydropower projects in strategic basins
Download Standing Committee Order (PDF)
Steering Committee for 13 Projects
Function: High-level policy oversight for strategic project cluster
Composition:
- Chief Minister / Deputy Chief Minister (Chair)
- Cabinet Ministers
- Chief Secretary
- DHPD Commissioner
- Project developers
- Central Ministry representatives
Responsibilities:
- Strategic policy decisions
- Inter-ministerial coordination
- Infrastructure planning
- Fund allocation
- Issue escalation resolution
- Performance review
Authority: Policy-level decision making for project cluster
Download Steering Committee Order (PDF)
Steering Committee for Small HEP
Function: Support and oversee small and mini hydropower projects
Scope: Projects below 25 MW capacity
Composition:
- DHPD Commissioner (Chair)
- CE Planning
- Development experts
- Community representatives
- NGO representatives
Responsibilities:
- Small project facilitation
- Technical support
- Environmental compliance
- Community engagement
- Streamlined approvals
- Performance monitoring
Features:
- Simplified approval procedures
- Local developer support
- Community-friendly approach
- Faster timelines
- Affordable implementation
Download Steering Committee Small HEP (PDF)
Clearance Process Timeline
Project Identification (0-3 months)
- Basin study findings
- Project selection
- Initial screening
Concession Bidding (3-6 months)
- Concession Committee notification
- Bidding process
- Developer selection
- Agreement execution
Feasibility Stage (6-18 months)
- Detailed design preparation
- Environmental Impact Assessment
- Social Impact Assessment
- Community consultations
- R&R planning
Clearance Stage (18-36 months)
- Environmental clearance (6-12 months)
- Forest clearance (3-6 months)
- Wildlife clearance (3-6 months)
- Other approvals (3-6 months)
Construction Start (36+ months)
- All clearances in place
- R&R plan approved
- Infrastructure ready
- Financial closure
- Construction begins
Compliance Monitoring
Monitoring Phases
Pre-Construction:
- Land acquisition compliance
- Environmental baseline establishment
- R&R readiness verification
- Community awareness programs
During Construction (Monthly/Quarterly):
- Schedule progress
- Environmental compliance
- Social safeguard implementation
- LADF utilization
- Grievance resolution
- Quality assurance
Operation Phase (Quarterly/Annual):
- Environmental management
- Social benefit delivery
- LADF implementation
- Performance benchmarking
- Long-term sustainability
Monitoring Reports
- Quarterly: SLMC meeting notes and action items
- Semi-annual: Compliance status reports
- Annual: Comprehensive compliance audit
- Environmental: Annual environmental audits
- Social: Annual social impact assessments
Grievance Redressal Mechanism
Levels of Grievance Redressal
Level 1: Project Developer
- First point of contact
- Local resolution attempt
- 15-day response target
Level 2: District Collector
- Escalation if developer unsatisfactory
- District-level review
- 30-day resolution target
Level 3: SLMC
- Multi-stakeholder review
- Technical assessment
- 60-day resolution
Level 4: DHPD Commissioner
- Final state-level decision
- Policy interpretation
- Appeal resolution
Grievance Categories
- Environmental impact issues
- Social impact and resettlement
- LADF utilization concerns
- Employment opportunities
- Community benefit delivery
- Contract matters
- Compensation disputes
Committee Documents Download
- Concession Committee
- State Level Monitoring Committee (SLMC)
- STEC Committee Order 2021
- Standing Committee 13 Projects
- Steering Committee 13 Projects
- Steering Committee Small HEP
Contact for Clearance Information
Commissioner, DHPD Email: commrdhpd.arn@gmail.com Phone: 8731931119 (PIO)
Civil Secretariat, Itanagar - 791111
Related Resources
Have questions about this page?